50 Most Expected Time & Work Questions for AFCAT 2026 with Answers & Shortcut Tricks


50 Most Expected Time & Work Questions

Important Time & Work Formulas

  • Work = Time × Efficiency
  • Efficiency = Work ÷ Time
  • If A completes a work in x days: One day's work = 1/x
  • Combined Work: If A takes Combined work per day = 1/x + 1/y

AFCAT Shortcut

  • If A takes 10 days and B takes 15 days
  • Together = (10×15)/(10+15) = 6 days

This shortcut works only when both start together and work continuously.

50 Most Expected Time & Work Questions for AFCAT 2026 with Answers & Shortcut Tricks

1. A alone can complete a work in 20 days. How many days will A and B together take if B alone can complete it in 30 days?

  • A. 10 days
  • B. 12 days
  • C. 15 days
  • D. 18 days

Solution

  • One day's work
  • A = 1/20
  • B = 1/30
  • Together = 1/20 + 1/30 = (3+2)/60 = 5/60 = 1/12

Hence, total time = 12 days

2. A can complete a work in 12 days. B can complete the same work in 18 days. How many days will they take together?

  • A. 6
  • B. 7.2
  • C. 8
  • D. 9

Solution

  • Combined Time = (12 ×18)/(12+18) =216/30 = 7.2 days

3. A completes a work in 15 days. After working alone for 5 days, how much work remains?

  • A. 1/3
  • B. 2/3
  • C. 3/5
  • D. 4/5

Solution

  • Work completed =5/15 =1/3
  • Remaining = 2/3

4. B alone completes a work in 24 days. How much work does he complete in 6 days?

  • A. 1/5
  • B. 1/4
  • C. 1/3
  • D. 1/2

5. A completes a work in 25 days, while B completes it in 20 days. Find the ratio of their efficiencies.

  • A. 4 : 5
  • B. 5 : 4
  • C. 20 : 25
  • D. 1 : 1

Solution

  • Efficiency is inversely proportional to time.
  • Efficiency Ratio =20:25 = 5:4

6. A can complete a work in 18 days, while B can complete it in 36 days. They work together. How many days will they take to complete the work?

  • A. 10 days
  • B. 12 days
  • C. 14 days
  • D. 15 days

Solution

  • One day's work: A = 1/18, B = 1/36
  • Together = 1/18 + 1/36 = 3/36 = 1/12

Hence, required time = 12 days

Shortcut

  • Combined Time = (18 × 36) ÷ (18 + 36) = 648 ÷ 54 = 12 day

7. A alone can complete a work in 24 days. B is 50% more efficient than A. In how many days can B alone complete the work?

  •  A. 14 days
  •  B. 16 days
  •  C. 18 days
  •  D. 20 days

Solution

  • If efficiency increases by 50%, Time decreases in the ratio 2 : 3 Time taken by B = 24 × 2/3 = 16 days

8. A can complete a work in 15 days and B in 10 days. They work together for 4 days. The remaining work is completed by A alone. How many more days will A take?

  • A. 3 days
  • B. 4 days
  • C. 5 days
  • D. 6 days

Solution

  • Combined work per day = 1/15 + 1/10 = 1/6
  • Work done in 4 days = 4/6 = 2/3
  • Remaining work = 1/3
  • A completes 1/15 work per day.
  • Required time = (1/3) ÷ (1/15) = 5 days
9. A can complete a work in 20 days. After working for 8 days, he leaves. What fraction of the work remains?
  • A. 2/5
  • B. 3/5
  • C. 4/5
  • D. 1/5

Solution

  • Completed work = 8/20 = 2/5
  • Remaining = 1 − 2/5 = 3/5
10. 12 men can complete a work in 15 daysHow many men are required to complete the same work in 9 days?
  • A. 18
  • B. 20
  • C. 22
  • D. 24

Solution

  • Men × Days = Constant
  • 12 × 15 = M × 9
  • M = 180 ÷ 9 = 20 men

Shortcut

M₁ × D₁ = M₂ × D₂

AFCAT Shortcut

Whenever only men and days are involved: Men × Days = Constant. This formula solves most questions instantly.

11. A completes a work in 30 days, while B completes it in 20 daysWorking together, how much work do they complete in 5 days?

  • A. 1/3
  • B. 5/12
  • C. 7/12
  • D. 3/4

Solution

  • Combined work = 1/30 + 1/20 = 5/60 = 1/12
  • Work in 5 days = 5 × 1/12 = 5/12

12. A is twice as efficient as B. If B completes a work in 24 days, in how many days will A complete it?

  • A. 10
  • B. 12
  • C. 14
  • D. 16

Solution

  • Efficiency doubles,
  • Time becomes half.
  • 24 ÷ 2 = 12 days
13. 15 workers complete a project in 16 daysHow many workers are needed to finish it in 12 days?
  • A. 18
  • B. 20
  • C. 22
  • D. 24

Solution

  • Workers × Days = Constant
  • 15 ×16 = W ×12
  • W =240 ÷12= 20 workers

14. A alone can complete a work in 40 days. B alone can complete it in 60 days. How much work will they complete together in 8 days?

  • A. 1/3
  • B. 2/5
  • C. 7/15
  • D. 8/15

Solution

  • Combined work =1/40 +1/60 =5/120 =1/24
  • In 8 days =8/24 = 1/3
15. A can complete a work in 25 days, while B can complete it in 50 daysThey work together for 10 daysHow much work remains?
  • A. 1/5
  • B. 2/5
  • C. 3/5
  • D. 4/5

Solution

  • Combined work per day =1/25 +1/50
  •  Work done in 10 days =30/50 =3/5
  •  Remaining =1−3/5 = 2/5

AFCAT Shortcut – LCM Method

If

  • A finishes a work in 12 days
  • B finishes it in 18 days

Take Total Work = LCM (12,18) = 36 units

Then,

  • A's efficiency = 36 ÷ 12 = 3 units/day
  • B's efficiency = 36 ÷ 18 = 2 units/day

Together = 5 units/day

Time = 36 ÷ 5 = 7.2 days

This method is faster than working with fractions.

16. A can complete a work in 12 days, while B can complete it in 18 days. Using the LCM method, how many days will they take together?
  • A. 6 days
  • B. 7.2 days
  • C. 8 days
  • D. 9 days

Solution

  • LCM = 36 units
  • A = 3 units/day
  • B = 2 units/day
  • Together = 5 units/day
  • Time = 36 ÷ 5 = 7.2 days
17. A completes a work in 15 days and B in 10 days. They work on alternate days, with A starting first. How many days will they take to finish the work?
  • A. 11 days
  • B. 12 days
  • C. 13 days
  • D. 14 days

Solution

  • LCM = 30 units
  • A = 2 units/day
  • B = 3 units/day
  • In 2 days, Work done = 5 units
  • After 10 days (5 cycles), Completed = 25 units
  • Remaining = 5 units
  • Day 11 (A): +2 = 27
  • Day 12 (B): +3 = 30
  • Hence, 12 days
18. A can complete a work in 24 days. B is twice as efficient as A. If they work together, in how many days will the work be completed?
  • A. 6 days
  • B. 8 days
  • C. 10 days
  • D. 12 days

Solution

  • A = 1 unit
  • B = 2 units
  • Total = 3 units
  • A alone = 24 days
  • Combined Time = 24 ÷ 3 = 8 days
19. 20 men complete a work in 24 days. After 12 days, 5 men leave. How many more days are required?
  • A. 14
  • B. 15
  • C. 16
  • D. 18

Solution

  • Total Work = 20 × 24 = 480 man-days
  • Completed = 20 × 12 = 240 man-days
  • Remaining = 240 man-days
  • Remaining Men = 15
  • Time = 240 ÷ 15 = 16 days
20. A can complete a work in 20 days, while B can complete it in 30 days. After working together for 6 days, B leaves. How many more days will A take?
  • A. 8
  • B. 9
  • C. 10
  • D. 11

Solution

  • Combined work = 1/20 + 1/30 = 1/12
  • Work done in 6 days = 6/12 = 1/2
  • Remaining work = 1/2
  • A alone takes = (1/2) ÷ (1/20) = 10 days
21. A is 50% more efficient than B. If B finishes a work in 30 days, how many days will A take?
  • A. 18
  • B. 20
  • C. 22
  • D. 24

Solution

  • Efficiency ratio - A : B = 3 : 2
  • Time ratio = 2 : 3
  • A's Time = 30 × 2/3 = 20 days
22. A completes a work in 16 days, while B completes it in 24 days. Working together, how much work will they complete in 6 days?
  • A. 5/8
  • B. 3/4
  • C. 7/8
  • D. 2/3

Solution

  • LCM = 48
  • A = 3 units/day
  • B = 2 units/day
  • Together = 5 units/day
  • In 6 days = 30 units
  •  Fraction completed = 30/48 = 5/8
23. 12 men can complete a work in 18 days. How many men are needed to complete the same work in 9 days?
  • A. 20
  • B. 22
  • C. 24
  • D. 26

Solution

  • Men × Days = Constant
  • 12 ×18 =216
  • Required Men =216 ÷9 = 24
24. A and B together complete a work in 15 days. If A alone completes it in 25 days, in how many days can B alone complete it?
  • A. 30
  • B. 35
  • C. 37.5
  • D. 40

Solution

  • B's work per day =1/15 −1/25 =(5−3)/75 =2/75
  • Time =75/2 = 37.5 days
25. A can complete a work in 18 days, while B can complete it in 27 days. They work together for 9 days. What fraction of the work remains?
  • A. 1/6
  • B. 1/5
  • C. 1/4
  • D. 1/3

Solution

  • LCM = 54 units
  • A = 3 units/day
  • B = 2 units/day
  • Together = 5 units/day
  • Work done in 9 days = 45 units
  • Remaining = 54 −45 = 9 units
  •  Fraction remaining = 9/54 = 1/6

26. A can complete a work in 16 days, while B can complete it in 24 days. They work together for 8 days, after which B leaves. How many more days will A alone take to finish the remaining work?

  • A. 3
  • B. 2
  • C. 5
  • D. 6

Solution

  • Work done together in 8 days = 8 × (1/16 + 1/24) = 8 × (5/48) = 5/6
  • Remaining work = 1/6
  • Time taken by A = (1/6) ÷ (1/16) = 16/6 = 8/3 ≈ 2.67 days 
27. A can complete a work in 18 days and B in 36 days. If they work together, in how many days will they complete 75% of the work?
  • A. 8 days
  • B. 9 days
  • C. 10 days
  • D. 12 days

Solution

  • Combined work = 1/18 + 1/36 = 1/12
  • Time for full work = 12 days
  • Time for 75% = 12 × 3/4 = 9 days

28. A is 25% more efficient than B. If B can complete a work in 20 days, how many days will A take?
  • A. 14
  • B. 15
  • C. 16
  • D. 18

Solution

  • Efficiency Ratio
  • A : B = 5 : 4
  • Time Ratio = 4 : 5
  • A's time = 20 × 4/5 = 16 days

29. 24 workers complete a project in 15 days. How many workers are required to complete the same work in 10 days?
  • A. 30
  • B. 32
  • C. 34
  • D. 36

Solution

  • Workers × Days = Constant
  • 24 × 15 = 360
  • Workers required = 360 ÷ 10 = 36
30. A completes a work in 30 days. B is twice as efficient as A. How many days will they take together?
  • A. 8
  • B. 10
  • C. 12
  • D. 15

Solution

  • Assume A = 1 unit/day
  • B = 2 units/day
  • Together = 3 units/day
  • Since A alone takes 30 days,
  • Together = 30 ÷ 3 = 10 days

AFCAT Shortcut

  • If one person is n times more efficient,
  • Their working time becomes 1/n in proportion.
  • Always convert efficiency into ratios before solving.

31. A can complete a work in 12 days and B in 20 days. If both work together for 4 days, what fraction of the work remains?

  • A. 2/15
  • B. 4/15
  • C. 7/15
  • D. 8/15

Solution

  • Combined work = 1/12 + 1/20 = 2/15
  • Work done in 4 days = 8/15
  • Remaining = 7/15

32. A and B together complete a work in 8 days. If A alone takes 24 days, how many days will B alone take?

  • A. 10
  • B. 12
  • C. 16
  • D. 18

Solution

  • B's work = 1/8 − 1/24 = 2/24 = 1/12
  • Time = 12 days

33. 15 men can complete a work in 20 days. After 5 days, 5 more men join them. How many additional days are required?

  • A. 9
  • B. 10
  • C. 11
  • D. 12

Solution

  • Total work = 15 × 20 = 300 man-days
  • Work completed in 5 days = 15 × 5 = 75
  • Remaining = 225
  • Workers now = 20
  • Time = 225 ÷ 20 = 11.25 days
  • Closest answer = 11 days

34. A completes a work in 40 days. B completes the same work in 60 days. How much work will they complete together in 12 days?

  • A. 1/2
  • B. 3/5
  • C. 2/3
  • D. 4/5

Solution

  • Combined work = 1/40 + 1/60 = 1/24
  • In 12 days = 12/24 = 1/2

35. A can complete a work in 25 days. He works alone for 10 days. What percentage of work remains?

  • A. 50%
  • B. 55%
  • C. 60%
  • D. 65%

Solution

  • Completed = 10/25 = 40%
  • Remaining = 60%

36. Two workers complete a work in 15 days. If one worker alone takes 30 days, how many days will the other worker take?

  • A. 25
  • B. 30
  • C. 35
  • D. 40

Solution

  • Other worker's efficiency = 1/15 − 1/30 = 1/30
  • Hence, Time = 30 days

37. A is 40% more efficient than B. If B completes a work in 28 days, A will complete it in

  • A. 18 days
  • B. 20 days
  • C. 22 days
  • D. 24 days

Solution

  • Efficiency ratio = 7 : 5
  • Time ratio = 5 : 7
  • Time = 28 × 5/7 = 20 days

38. 18 workers can complete a work in 16 days. How many workers are required to complete it in 12 days?

  • A. 22
  • B. 24
  • C. 26
  • D. 28

Solution

  • 18 × 16 = 288
  • Workers = 288 ÷ 12 = 24

39. A and B together complete a work in 10 days. If A alone takes 15 days, B alone will take

  • A. 25 days
  • B. 30 days
  • C. 35 days
  • D. 40 days

Solution

  • B's work = 1/10 − 1/15 = 1/30
  • Time = 30 days

40. A completes a work in 24 days, B in 36 days, and C in 72 days. How many days will all three together take?

  • A. 12
  • B. 14.4
  • C. 16
  • D. 18

Solution

  • Combined work = 1/24 + 1/36 + 1/72 = (3 + 2 + 1)/72 = 6/72 = 1/12

AFCAT Quick Revision

Remember these formulas:

  • One Day Work = 1 ÷ Days
  • Efficiency ∝ 1 ÷ Time
  • Workers × Days = Constant
  • LCM Method saves time
  • Work Done = Rate × Time

41. A can complete a work in 15 days, while B can complete it in 10 days. If both work together, in how many days will they finish the work?

  • A. 5 days
  • B. 6 days
  • C. 7 days
  • D. 8 days

Solution

  • Combined work = 1/15 + 1/10 = 5/30 = 1/6
  • Required Time = 6 days

42. A completes a work in 18 days. B is 50% more efficient than A. How many days will B take?

  • A. 10 days
  • B. 12 days
  • C. 14 days
  • D. 16 days

Solution

  • A : B Efficiency = 2 : 3
  • Time Ratio = 3 : 2
  • Time taken by B = 18 ×2/3 = 12 days

43. 20 men can complete a work in 24 days. After 8 days, 5 men leave. How many more days are required?

  • A. 18 days
  • B. 19 days
  • C. 20 days
  • D. 21 days

Solution

  • Total Work =20 ×24 =480 man-days
  • Completed =20 ×8 =160
  • Remaining =320
  • Remaining workers =15
  • Time =320 ÷15 ≈21.33 days

44. A and B together complete a work in 12 days. If A alone completes it in 20 days, B alone will complete it in

  • A. 24 days
  • B. 28 days
  • C. 30 days
  • D. 32 days

Solution

  • B's work =1/12−1/20 =(5−3)/60 =1/30
  • Hence, Time = 30 days

45. A can complete a work in 25 days. After working alone for 15 days, what percentage of work remains?

  • A. 20%
  • B. 30%
  • C. 40%
  • D. 50%

Solution

  • Completed =15/25 =60%
  • Remaining = 40%

AFCAT Shortcut

  • If a person works for x days out of y total days
  • Completed Work = x/y
  • Remaining Work = (y−x)/y

46. A is twice as efficient as B. Both start working together. If B alone takes 30 days, together they complete the work in

  • A. 8 days
  • B. 10 days
  • C. 12 days
  • D. 15 days

Solution

  • Efficiency
  • A =2:1
  • Total Efficiency =3 units
  • Time =30 ÷3 = 10 days

47. A, B and C can complete a work individually in 24, 36 and 72 days respectively. How many days will all three together take?

  • A. 10 days
  • B. 11 days
  • C. 12 days
  • D. 14 days

Solution

  • Combined work =1/24+1/36+1/72 =(3+2+1)/72 =6/72 =1/12
  • Required Time = 12 days

48. 18 workers complete a work in 15 days. How many workers are required to finish it in 9 days?

  • A. 28
  • B. 30
  • C. 32
  • D. 34

Solution

  • Workers × Days = Constant
  • 18 ×15 =270
  • Workers =270 ÷9 = 30

49. A can complete a work in 30 days, while B completes it in 20 days. They work together for 8 days. What fraction of work remains?

  • A. 1/3
  • B. 2/5
  • C. 3/5
  • D. 4/5

Solution

  • Combined work =1/30+1/20 =1/12
  • Work completed =8/12 =2/3
  • Remaining = 1/3

50. A can complete a work in 12 days, B in 18 days, and C in 36 days. They work together for 4 days. What fraction of work remains?

  • A. 1/6
  • B. 2/9
  • C. 1/3
  • D. 4/9

Solution

  • Combined work =1/12+1/18+1/36 =(3+2+1)/36 =6/36 =1/6
  • Work completed in 4 days =4/6 =2/3
  • Remaining = 1/3

Complete Time & Work Formula Sheet

  • One Day Work = 1 ÷ Total Days
  • Work = Efficiency × Time
  • Efficiency = Work ÷ Time = 1/x + 1/y = (x × y) ÷ (x + y)

(Only when two people work together continuously.)

  • Men × Days = Constant
  • Efficiency ∝ 1 ÷ Time

Quick Revision Table

Concept Formula
One Day Work 1/Days
Combined Work 1/x + 1/y
Combined Time xy/(x+y)
Efficiency Work ÷ Time
Men & Days Constant
Remaining Work Total − Completed

Last-Minute AFCAT Tips

  • Use the LCM Method wherever possible.
  • Never solve combined work questions using long fractions if an LCM simplifies the calculations.
  • Memorize the Combined Time Formula for two workers.
  • Focus on efficiency ratios instead of actual work whenever possible.
  • Practice alternate working and men-days questions regularly.